A 100 MW solar plant typically needs about 400 to 500 acres. A 500 acre parcel can support roughly 100 to 125 MW, and 1,000 acres roughly 200 to 250 MW, if the land is usable, contiguous and has a grid connection. This guide explains those figures, buying versus leasing, multiple ownership, and gives a full checklist.
How much land per MW
Solar park guidelines in India have used about 5 acres per MW as a baseline, and some states use 4 acres per MW as a minimum. Modern high-efficiency modules can reduce this; single-axis trackers, wider row spacing and a high DC to AC ratio can increase it. Always calculate on usable area, after removing:
- Setbacks from boundaries and roads
- Nallas, streams and drainage paths
- Internal roads, the substation and buildings
- Shaded or steep areas
- Gaps where owners did not sell or lease
| Plant size | Approx. land at 4–5 acres/MW |
|---|---|
| 50 MW | 200–250 acres |
| 100 MW | 400–500 acres |
| 200 MW | 800–1,000 acres |
| 500 MW | 2,000–2,500 acres |
Planning ranges only. Your engineering design decides the final figure.
500 and 1,000 acre requirements
At this scale the land itself is rarely the hardest part. Developers usually look for:
- A grid connection point with enough capacity, often at 132 kV, 220 kV or higher
- A short, buildable route for the transmission line
- As few owners as possible, with clear titles
- One contiguous block, or a small number of large blocks close together
- Low-value or uncultivated land to reduce displacement and local opposition
- All-weather road access for heavy vehicles
16pur.com currently lists several parcels of 600 to 1,500 acres in Solapur district and one in Ahilyanagar. See them on the solar project land page. Their contiguity and ownership are To be confirmed.
Buying or leasing land for solar in Maharashtra
Most large parcels are agricultural land. Maharashtra law generally restricts the purchase of agricultural land by non-agriculturists. Section 63-1A of the Maharashtra Tenancy and Agricultural Lands Act allows purchase for bona fide industrial use, subject to conditions including time limits to start use. The law was amended again in 2026. Whether a solar project qualifies in a particular case is a legal question for your lawyer.
Leasing is common. A registered long-term lease should cover the full project life plus decommissioning, escalation, access rights, cable and line corridors, and what happens at the end of the term. For reference, MSEDCL’s MSKVY 2.0 scheme offers private landowners ₹1.25 lakh per hectare per year with 3% annual escalation. That is a scheme rate, not a market rate for private projects.
| Factor | Purchase | Lease |
|---|---|---|
| Upfront cost | High | Low |
| Legal route for companies | May need an exemption | Generally simpler; must be registered |
| Control | Full | For the term only |
| Exit | Sell the land | Return the land, restore as agreed |
Contiguous land and multiple ownership
A parcel described as “500 acres” is often many survey numbers held by different families. Before relying on the acreage:
- List every survey and gat number, with its area and owners from the 7/12
- Plot them on the village map to confirm they touch
- Check mutation entries for recent transfers, inheritance and disputes
- Identify tenants, co-owners and anyone with rights on the land
- Confirm government land, roads or nallas that cut through the block
- Agree a plan for owners who will not join
Solar project land due diligence checklist
| Area | Checks |
|---|---|
| Title | 7/12 and 8A extracts, mutation entries, 30-year search report, encumbrances, pending cases |
| Ownership | All owners and heirs identified; consent of each |
| Survey | Boundary measurement, contiguity, village map, internal roads and nallas |
| Land use | Classification, tenure (e.g. inam, watan, new tenure), conversion requirements |
| Access | Legal right of way from public road; heavy-vehicle route |
| Grid | Substation capacity, voltage, line route and right of way, connectivity approval |
| Technical | Solar resource, topography, soil, drainage, flood history, shading |
| Environment and social | Protected areas, forest land, water bodies, local concerns |
| Commercial | Price or rent, escalation, payment schedule, taxes and stamp duty |
Start with the records on Mahabhumi Bhulekh, and read our guide to documents to check before buying property. This checklist is general information, not legal advice.
Frequently asked questions
How much land do I need for a 500 MW solar project?
At a planning figure of about 4 to 5 acres per MW, roughly 2,000 to 2,500 acres. Your design may need more or less.
What can I build on 1,000 acres?
Roughly 200 to 250 MW of solar at 4 to 5 acres per MW, if the usable area is close to the total and the grid can take it.
What if a 500 acre parcel has 40 owners?
Each owner must agree and sign. Map every survey number, check each 7/12 and mutation history, and plan for owners who will not sell or lease.
Should I buy or lease?
It depends on your financing, the land classification and the project life. Leasing avoids some purchase restrictions on agricultural land and lowers upfront cost. Buying gives full control. Take legal and tax advice.
Related pages
Land for solar power projects in Solapur
Listings and solar site requirements.
Large project land in Maharashtra
All sectors and large listings.
Stamp duty and registration in Solapur
Costs to plan for when buying land.
Sources
- Energetica India: MNRE scheme for solar parks (land of about 5 acres per MW)
- Renewable Watch: Haryana solar park guidelines (minimum 4 acres per MW)
- Cyril Amarchand Mangaldas: Using agricultural land for non-agricultural purposes in Maharashtra (Section 63-1A)
- JSA: Maharashtra tenancy law amendment, June 2026
- MSEDCL: Mukhyamantri Saur Krushi Vahini Yojana 2.0 FAQ (land lease terms)
- Mahabhumi Bhulekh: 7/12 and 8A land records
Policy and scheme terms change. Check the current official text before relying on any figure.
Project requirement form
Name, phone, project type and acreage are enough to start. Other fields are optional. Your details go only to Mandar Kulkarni at 16pur.com.
Send your project requirement
Looking for land for a solar, wind–solar, data centre or warehousing project? Share your acreage, budget, purchase or lease preference, and infrastructure requirements with Mandar Kulkarni.
Mandar Kulkarni
Kulkarni Patil Infracon Estates LLP
+91 80876 40953
mandar@16pur.com
Flat No. 501, Sukhada Appt, Vaman Nagar, Jule Solapur, Solapur – 413004, Maharashtra, India